Dept. of Trans. PROGRESS Serial No. Contract No. 00-203-14-10 03-430004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 6% 24% 03-SAC-80-M10.2/18.0 Federal Project: 03-PLA-80-0.4/0.8 ACIM-080-3(223) G-080-3(223) ACST-P051(17) Progress payment No. 01 Payment period ending: 07-20-00 RICHARD A HEAPS ELECTRICAL CONTRACTOR INC 8909 FLORIN ROAD SACRAMENTO CA 95825 Escrow No. 01479 Total Estimate This Estimate 1. Contract Itms Without Mobil. 129,591.77 129,591.77 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 129,591.77 129,591.77 5. Mobilization 29,238.00 29,238.00 6. Total Work Completed 158,829.77 7. Deductions 8. a.Contract Retentions -12,959.18 -12,959.18 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 145,870.59 145,870.59 10. Reduction Amt to Escrow 11. Payment to Escrow 12,950.00 12. Net Pymt. this Estimate 145,870.59