Dept. of Trans. PROGRESS Serial No. Contract No. 01-205-12-43 03-430104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 21% 18% 03-YOL-50-0.0/3.1 Federal Project: 03-SAC-50-L0.1/16.8 ACNH-000C(235) Progress payment No. 01 Payment period ending: 07-20-01 ROYAL ELECTRIC COMPANY P O BOX 231430 SACRAMENTO CA 95823 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 568,820.00 568,820.00 2.a. Extra Work b. Adjustment Comp. -20,832.00 -20,832.00 3. Materials on Hand 4. Earned Subject to Retention 547,988.00 547,988.00 5. Mobilization 112,500.00 112,500.00 6. Total Work Completed 660,488.00 7. Deductions 8. a.Contract Retentions -54,798.80 -54,798.80 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 605,689.20 605,689.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 605,689.20