Dept. of Trans. PROGRESS Serial No. Contract No. 01-235-08-31 03-430104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 34% 35% 03-YOL-50-0.0/3.1 Federal Project: 03-SAC-50-L0.1/16.8 ACNH-000C(235) Progress payment No. 02 Payment period ending: 08-20-01 ROYAL ELECTRIC COMPANY P O BOX 231430 SACRAMENTO CA 95823 Escrow No. 01649 Total Estimate This Estimate 1. Contract Itms Without Mobil. 954,710.00 385,890.00 2.a. Extra Work b. Adjustment Comp. -20,832.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 933,878.00 385,890.00 5. Mobilization 142,500.00 30,000.00 6. Total Work Completed 1,076,378.00 7. Deductions 8. a.Contract Retentions -59,456.00 -4,657.20 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,016,922.00 411,232.80 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 411,232.80