Dept. of Trans. PROGRESS Serial No. Contract No. 01-264-14-45 03-430104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 45% 52% 03-YOL-50-0.0/3.1 Federal Project: 03-SAC-50-L0.1/16.8 ACNH-000C(235) Progress payment No. 03 Payment period ending: 09-20-01 ROYAL ELECTRIC COMPANY P O BOX 231430 SACRAMENTO CA 95823 Escrow No. 01649 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,268,711.25 314,001.25 2.a. Extra Work b. Adjustment Comp. -20,832.00 0.00 3. Materials on Hand 93,752.68 93,752.68 4. Earned Subject to Retention 1,341,631.93 407,753.93 5. Mobilization 142,500.00 0.00 6. Total Work Completed 1,390,379.25 7. Deductions 8. a.Contract Retentions -67,081.60 -7,625.60 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,417,050.33 400,128.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 400,128.33