Dept. of Trans. PROGRESS Serial No. Contract No. 01-355-15-16 03-430104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 100% 03-YOL-50-0.0/3.1 Federal Project: 03-SAC-50-L0.1/16.8 ACNH-000C(235) Progress payment No. 06 Payment period ending: 12-20-01 ROYAL ELECTRIC COMPANY P O BOX 231430 SACRAMENTO CA 95823 Escrow No. 01649 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,624,112.20 579,574.00 2.a. Extra Work b. Adjustment Comp. -20,832.00 0.00 3. Materials on Hand 93,752.68 -126,900.00 4. Earned Subject to Retention 2,697,032.88 452,674.00 5. Mobilization 150,000.00 0.00 6. Total Work Completed 2,753,280.20 7. Deductions 8. a.Contract Retentions -134,851.64 -22,633.70 b. Unsatisfactory Prog. -22,633.70 -22,633.70 c. Reduction after 95% Comp. 9. Total pay to Contractor 2,689,547.54 407,406.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 407,406.60