Dept. of Trans. PROGRESS Serial No. Contract No. 02-022-14-57 03-430104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 92% 98% 03-YOL-50-0.0/3.1 Federal Project: 03-SAC-50-L0.1/16.8 ACNH-000C(235) Progress payment No. 07 Payment period ending: 01-18-02 ROYAL ELECTRIC COMPANY P O BOX 231430 SACRAMENTO CA 95823 Escrow No. 01649 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,842,822.20 218,710.00 2.a. Extra Work b. Adjustment Comp. -20,832.00 0.00 3. Materials on Hand 0.00 -93,752.68 4. Earned Subject to Retention 2,821,990.20 124,957.32 5. Mobilization 150,000.00 0.00 6. Total Work Completed 2,971,990.20 7. Deductions 8. a.Contract Retentions -141,099.51 -6,247.87 b. Unsatisfactory Prog. -28,881.56 -6,247.86 c. Reduction after 95% Comp. 9. Total pay to Contractor 2,802,009.13 112,461.59 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 112,461.59