Dept. of Trans. PROGRESS Serial No. Contract No. 02-204-16-19 03-430104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 99% 03-YOL-50-0.0/3.1 Federal Project: 03-SAC-50-L0.1/16.8 ACNH-000C(235) Progress payment No. 10 Payment period ending: 07-19-02 ROYAL ELECTRIC COMPANY P O BOX 231430 SACRAMENTO CA 95823 Escrow No. 01649 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,998,955.00 9,800.00 2.a. Extra Work 32,574.81 1,532.50 b. Adjustment Comp. -79.15 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,031,450.66 11,332.50 5. Mobilization 150,000.00 0.00 6. Total Work Completed 3,181,450.66 7. Deductions 8. a.Contract Retentions -151,572.53 -566.62 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,029,878.13 10,765.88 10. Reduction Amt to Escrow 11. Payment to Escrow 151,570.00 12. Net Pymt. this Estimate 10,765.88