Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 02-310-11-31 03-430104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-YOL-50-0.0/3.1 Federal Project: 03-SAC-50-L0.1/16.8 ACNH-000C(235) Progress payment No. 12 Payment period ending: 08-13-02 ROYAL ELECTRIC COMPANY P O BOX 231430 SACRAMENTO CA 95823 Escrow No. 01649 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,001,955.00 0.00 2.a. Extra Work 34,737.79 2,162.98 b. Adjustment Comp. 24,744.97 -1,153.36 3. Materials on Hand 4. Earned Subject to Retention 3,061,437.76 1,009.62 5. Mobilization 150,000.00 0.00 6. Total Work Completed 3,211,437.76 7. Deductions -10,812.50 15,187.50 8. a.Contract Retentions -151,572.53 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 151,572.53 0.00 9. Total pay to Contractor 3,200,625.26 16,197.12 10. Reduction Amt to Escrow -151,570.00 0.00 11. Payment to Escrow 151,570.00 12. Net Pymt. this Estimate 16,197.12