Dept. of Trans. PROGRESS Serial No. Contract No. 12-082-13-56 03-441614 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 03-SAC-50-R5.3/12.8 Federal Project: CMLN-6203(33) Progress payment No. 28 Payment period ending: 03-20-12 DE SILVA GATES MCM A JOINT VENTURE OF DE SILVA GATES CONSTRUCTION AND MCM CONSTRUCTION P O BOX 2909 DUBLIN CA 94568Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 49,253,099.35 -62,854.40 2.a. Extra Work 6,187,612.79 1,192,853.31 b. Adjustment Comp. 2,170,521.17 -4,639.54 3. Materials on Hand 86,900.00 -630,162.54 4. Earned Subject to Retention 57,698,133.31 495,196.83 5. Mobilization 5,850,000.00 0.00 6. Total Work Completed 63,461,233.31 7. Deductions -34,900.00 -7,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 63,513,233.31 488,196.83 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 488,196.83