Dept. of Trans. PROGRESS Serial No. Contract No. 05-082-15-28 03-4416U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 03-SAC-50-12.2/23.1 Federal Project: ACNH-P050(103) CMLN-6157(10) Progress payment No. 48 Payment period ending: 03-18-05 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01723 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,310,464.59 17,488.00 2.a. Extra Work 1,486,938.63 19,615.08 b. Adjustment Comp. 1,117,737.02 -142.15 3. Materials on Hand 4. Earned Subject to Retention 31,915,140.24 36,960.93 5. Mobilization 1,800,000.00 0.00 6. Total Work Completed 33,715,140.24 7. Deductions -37,195.30 -28,451.17 8. a.Contract Retentions -1,595,757.01 -1,848.04 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 32,082,187.93 6,661.72 10. Reduction Amt to Escrow 11. Payment to Escrow 1,595,750.00 12. Net Pymt. this Estimate 6,661.72