Dept. of Trans. PROGRESS Serial No. Contract No. 05-236-12-54 03-4416U4 PROGRESS PAYMENT VOUCHER %complete: %time: Location: PEP SAT 03-SAC-50-12.2/23.1 Federal Project: ACNH-P050(103) CMLN-6157(10) Progress payment No. 53 Payment period ending: 08-19-05 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 01723 Total Estimate This Estimate 1. Contract Itms Without Mobil. 29,325,658.59 3,103.00 2.a. Extra Work 1,487,376.28 0.00 b. Adjustment Comp. 1,104,003.43 0.00 3. Materials on Hand 4. Earned Subject to Retention 31,917,038.30 3,103.00 5. Mobilization 1,800,000.00 0.00 6. Total Work Completed 33,717,038.30 7. Deductions -19,744.13 -2,000.00 8. a.Contract Retentions -1,595,934.04 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 32,101,360.13 1,103.00 10. Reduction Amt to Escrow 11. Payment to Escrow 1,595,750.00 12. Net Pymt. this Estimate 1,103.00