Dept. of Trans. PROGRESS Serial No. Contract No. 05-115-15-52 03-4A0404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 94% 94% 03-SAC-5-23.8/24.2 Federal Project: ACIM-005-6(319) Progress payment No. 07 Payment period ending: 04-20-05 CALIFORNIA ENGINEERING CONTRACTORS INC 20 HAPPY VALLEY ROAD PLEASANTON CA 94566 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 732,114.00 6,850.00 2.a. Extra Work 95,034.04 20,740.04 b. Adjustment Comp. 6,677.00 10,607.00 3. Materials on Hand 4. Earned Subject to Retention 833,825.04 38,197.04 5. Mobilization 91,000.00 0.00 6. Total Work Completed 924,825.04 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 924,825.04 38,197.04 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 38,197.04