Dept. of Trans. PROGRESS Serial No. Contract No. 11-269-09-04 03-4A2404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 88% 65% 03-NEV-80-R5.6/ .0 Federal Project: ACIM-804-4(189) G-804-4(189) Progress payment No. 17 Payment period ending: 09-20-11 FLINTCO PACIFIC INC 401 DEREK PLACE ROSEVILLE, CA 95678 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,949,081.30 515,808.00 2.a. Extra Work 123,080.10 0.00 b. Adjustment Comp. -10,807.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,061,354.40 515,808.00 5. Mobilization 6. Total Work Completed 4,061,354.40 7. Deductions -46,057.50 -8,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 4,015,296.90 507,808.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 507,808.00