Dept. of Trans. PROGRESS Serial No. Contract No. 06-170-08-52 03-4A5104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 22% 46% 03-YUB-49-6.9/9.4 Federal Project: NONE Progress payment No. 03 Payment period ending: 06-16-06 THUNDER MOUNTAIN ENTERPRISES INC P O BOX 292821 SACRAMENTO CA 95829 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 100,003.62 75,108.57 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 100,003.62 75,108.57 5. Mobilization 26,145.00 8,715.00 6. Total Work Completed 126,148.62 7. Deductions -7,608.35 -7,510.85 8. a.Contract Retentions -10,000.36 -7,510.85 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 108,539.91 68,801.87 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 68,801.87