Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 09-349-10-00 03-4A6504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-PLA-80-R56.0/R65.0 Federal Project: NONE Progress payment No. 05 Payment period ending: 10-22-09 LORANG BROTHERS CONSTRUCTION INC 1175 S AUBURN STREET COLFAX CA 95713 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,219,942.50 17,414.15 2.a. Extra Work 100,073.48 40,438.35 b. Adjustment Comp. 93,035.40 2,260.78 3. Materials on Hand 4. Earned Subject to Retention 1,413,051.38 60,113.28 5. Mobilization 62,000.00 0.00 6. Total Work Completed 1,475,051.38 7. Deductions -11,000.00 1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,464,051.38 61,113.28 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 61,113.28