Dept. of Trans. PROGRESS Serial No. Contract No. 09-236-11-00 03-4C0904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 11% 0% 03-ED-49-6.6/8.3 Federal Project: SARR-P049(143) A-P049(143) Progress payment No. 02 Payment period ending: 08-20-09 DOUG VEERKAMP GENERAL ENGINEERING INC 2585 COLD SPRINGS ROAD PLACERVILLE CA 95667 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 341,631.56 191,582.30 2.a. Extra Work 19,448.77 19,448.77 b. Adjustment Comp. 3. Materials on Hand 34,812.58 34,812.58 4. Earned Subject to Retention 395,892.91 245,843.65 5. Mobilization 142,500.00 142,500.00 6. Total Work Completed 503,580.33 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 533,392.91 383,343.65 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 383,343.65