Dept. of Trans. PROGRESS Serial No. Contract No. 07-232-19-12 03-4C1104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 96% 95% 03-ED-50-18.5/ .0 Federal Project: NONE Progress payment No. 04 Payment period ending: 08-20-07 R N R CONSTRUCTION INC 8811 MESA BROOK WAY ELK GROVE CA 95624 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 365,777.50 34,625.00 2.a. Extra Work 7,926.88 5,868.35 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 373,704.38 40,493.35 5. Mobilization 39,000.00 0.00 6. Total Work Completed 412,704.38 7. Deductions -11,000.00 -3,000.00 8. a.Contract Retentions -18,685.22 -2,024.67 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 383,019.16 35,468.68 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 35,468.68