Dept. of Trans. PROGRESS Serial No. Contract No. 07-233-08-59 03-4C2504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 95% 61% 03-ED-89-16.6/16.7 Federal Project: ACST-P089(89) P-P089(89) Progress payment No. 04 Payment period ending: 08-20-07 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,190,918.72 95,554.32 2.a. Extra Work 77,328.02 28,667.08 b. Adjustment Comp. -5,142.49 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,263,104.25 124,221.40 5. Mobilization 132,026.60 0.00 6. Total Work Completed 1,395,130.85 7. Deductions -4,000.00 -4,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,391,130.85 120,221.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 120,221.40