Dept. of Trans. FINAL Serial No. Contract No. 07-307-15-10 03-4C2604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-ED-193-R6.2/ .0 Federal Project: ACST-S193(8) PH-S193(8) Progress payment No. 06 Payment period ending: 11-14-06 MARTIN GENERAL ENGINEERING INC 12485 QUICKSILVER DR RANCHO CORDOVA, CA 95742 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 569,197.72 0.00 2.a. Extra Work 40,940.21 3,219.75 b. Adjustment Comp. 2,443.93 0.00 3. Materials on Hand 4. Earned Subject to Retention 612,581.86 3,219.75 5. Mobilization 6. Total Work Completed 612,581.86 7. Deductions -12,500.00 18,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 600,081.86 21,219.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 21,219.75