Dept. of Trans. FINAL Serial No. Contract No. 07-307-14-37 03-4C3904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SUT-20-16.7/17.0 Federal Project: NONE Progress payment No. 20 Payment period ending: 05-25-07 VIKING CONSTRUCTION COMPANY INC P O BOX 1508 RANCHO CORDOVA CA 95741 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 520,735.60 0.00 2.a. Extra Work 27,432.21 4,976.53 b. Adjustment Comp. -8,175.54 -10,049.72 3. Materials on Hand 4. Earned Subject to Retention 539,992.27 -5,073.19 5. Mobilization 49,000.00 0.00 6. Total Work Completed 588,992.27 7. Deductions 0.00 3,600.00 8. a.Contract Retentions -26,562.38 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 26,562.38 0.00 9. Total pay to Contractor 588,992.27 -1,473.19 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -1,473.19