Dept. of Trans. FINAL Serial No. Contract No. 06-047-13-23 03-4C7504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-5-22.5/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-14-05 MARTIN BROTHERS CONSTRUCTION 20 LIGHT SKY COURT SACRAMENTO, CA 95828 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 126,858.00 0.00 2.a. Extra Work 48,435.15 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 175,293.15 0.00 5. Mobilization 6. Total Work Completed 175,293.15 7. Deductions -1,075.00 3,750.00 8. a.Contract Retentions -2,340.00 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 2,340.00 0.00 9. Total pay to Contractor 174,218.15 3,750.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,750.00