Dept. of Trans. PROGRESS Serial No. Contract No. 08-264-14-16 03-4E1104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 80% 84% 03-ED-50-0.9/17.2 Federal Project: NONE Progress payment No. 06 Payment period ending: 09-19-08 STEINY AND COMPANY INC P O BOX 3008 VALLEJO CA 94590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,311,644.60 384,429.20 2.a. Extra Work 6,482.77 6,482.77 b. Adjustment Comp. -9,347.79 -9,347.79 3. Materials on Hand 4. Earned Subject to Retention 1,308,779.58 381,564.18 5. Mobilization 6. Total Work Completed 1,308,779.58 7. Deductions -1,900.00 -1,000.00 8. a.Contract Retentions -65,438.98 -19,078.21 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,241,440.60 361,485.97 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 361,485.97