Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 11-210-13-48 03-4E2204 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-SAC-16-15.1/15.5 Federal Project: HSST-P016(35) P-P016(35) Progress payment No. 03 Payment period ending: 07-20-11 TEICHERT CONSTRUCTION P O BOX 15144 SACRAMENTO CA 958510144 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 287,996.85 17,361.85 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 287,996.85 17,361.85 5. Mobilization 6. Total Work Completed 287,996.85 7. Deductions -30,000.00 -30,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 257,996.85 -12,638.15 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -12,638.15