Dept. of Trans. PROGRESS Serial No. Contract No. 09-236-10-54 03-4E3604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 27% 40% 03-PLA-80-17.3/1.6 Federal Project: NONE Progress payment No. 02 Payment period ending: 08-20-09 ROADWAY ELECTRICAL WORKS INCORPORATED P O BOX 5083 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 87,760.25 54,194.50 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 87,760.25 54,194.50 5. Mobilization 31,920.00 15,120.00 6. Total Work Completed 119,680.25 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 114,680.25 64,314.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 64,314.50