Dept. of Trans. PROGRESS Serial No. Contract No. 09-296-14-11 03-4E4104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 100% 03-ED-50-67.8/68.6 Federal Project: NONE Progress payment No. 01 Payment period ending: 10-20-09 STEELHEAD CONSTRUCTORS INC P O BOX 997 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 82,663.00 82,663.00 2.a. Extra Work 4,682.43 4,682.43 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 87,345.43 87,345.43 5. Mobilization 6. Total Work Completed 87,345.43 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 87,345.43 87,345.43 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 87,345.43