Dept. of Trans. PROGRESS Serial No. Contract No. 09-328-17-20 03-4E4104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 72% 73% 03-ED-50-67.8/68.6 Federal Project: NONE Progress payment No. 02 Payment period ending: 11-19-09 STEELHEAD CONSTRUCTORS INC P O BOX 997 PALO CEDRO CA 96073 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 473,383.00 390,720.00 2.a. Extra Work 18,714.00 14,031.57 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 492,097.00 404,751.57 5. Mobilization 6. Total Work Completed 492,097.00 7. Deductions -5,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 487,097.00 399,751.57 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 399,751.57