Dept. of Trans. PROGRESS Serial No. Contract No. 09-267-15-36 03-4E4704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 64% 03-YUB-5714 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-17-09 SGC CONSTRUCTION P O BOX 3329 YUBA CITY CA 95993 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 115,746.43 11,850.72 2.a. Extra Work 4,467.04 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 120,213.47 11,850.72 5. Mobilization 6. Total Work Completed 120,213.47 7. Deductions -2,000.00 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 118,213.47 9,850.72 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 9,850.72