Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 10-313-10-10 03-4E6104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-NEV-89-0.1/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 10-29-10 KOCH EXCAVATING INC P O BOX 909 PENN VALLEY CA 95946 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 242,135.89 4,176.24 2.a. Extra Work 7,192.82 1,979.23 b. Adjustment Comp. -6,013.70 -6,013.70 3. Materials on Hand 4. Earned Subject to Retention 243,315.01 141.77 5. Mobilization 6. Total Work Completed 243,315.01 7. Deductions -16,000.00 -16,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 227,315.01 -15,858.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -15,858.23