Dept. of Trans. FINAL Serial No. Contract No. 11-026-11-06 03-4E6104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 03-NEV-89-0.1/ .0 Federal Project: NONE Progress payment No. 05 Payment period ending: 10-29-10 KOCH EXCAVATING INC P O BOX 909 PENN VALLEY CA 95946 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 242,135.89 0.00 2.a. Extra Work 7,192.82 0.00 b. Adjustment Comp. -6,013.70 0.00 3. Materials on Hand 4. Earned Subject to Retention 243,315.01 0.00 5. Mobilization 6. Total Work Completed 243,315.01 7. Deductions 0.00 1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 243,315.01 1,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,000.00