Dept. of Trans. PROGRESS Serial No. Contract No. 22-112-11-11 03-4E62U4 PROGRESS PAYMENT VOUCHER %complete: %time: 60% 91% Location: Federal Project: 03-ED-50-18.5/24.2 ACNH-P050(152) Progress payment No. 023 Payment period ending: 04-20-22 SECURITY PAVING COMPANY INC 3075 TOWNSGATE RD #200 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 12,148,319.61 407,284.86 2. a. Extra Work 243,086.65 0.00 b. Adustment Comp. 240,566.75 0.00 3. Materials on Hand 81,300.00 0.00 4. Earned Subject to Retention 12,713,273.01 407,284.86 5. Mobilization 2,500,000.00 0.00 6. Total Work Completed 15,131,973.01 7. Deductions -162,241.08 10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions -219,886.24 -40,728.49 c. Reduction after 95% Comp. 9. Total pay to Contractor 14,831,145.69 376,556.37 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 376,556.37