Dept. of Trans. SEMI-FINAL Serial No. Contract No. 17-072-11-37 03-4E8604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-PLA-193-4.4/5.4 HSST-P--(---) -----P193(12) Progress payment No. 013 Payment period ending: 01-30-17 TEICHERT CONSTRUCTION 4401 DULUTH AVE ROCKLIN CA 95765 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 4,492,663.60 74,432.68 2. a. Extra Work 319,275.30 56,109.87 b. Adustment Comp. 212,818.89 226,515.12 3. Materials on Hand 4. Earned Subject to Retention 5,024,757.79 357,057.67 5. Mobilization 510,054.70 0.00 6. Total Work Completed 5,534,812.49 7. Deductions -11,000.00 30,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 5,523,812.49 387,057.67 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 387,057.67