Dept. of Trans. PROGRESS Serial No. Contract No. 13-317-10-07 03-4F0304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 91% 50% 03-SIE-80-0.7/0.7 Federal Project: NHS Progress payment No. 02 Payment period ending: 10-18-13 GRANITE CONSTRUCTION COMPANY P.O. BOX 50085 WATSONVILLE, CA 95077 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 486,632.67 243,247.56 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 486,632.67 243,247.56 5. Mobilization 6. Total Work Completed 486,632.67 7. Deductions -20,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 466,632.67 233,247.56 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 233,247.56