Dept. of Trans. SEMI-FINAL Serial No. Contract No. 18-212-08-14 03-4F0604 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-GLE-5-0.0/20.0 ACNH-I005-7(98) Progress payment No. 010 Payment period ending: 01-12-18 TEICHERT CONSTRUCTION PO BOX 13557 SACRAMENTO CA 95853 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 18,770,082.20 0.00 2. a. Extra Work 1,211,663.74 240,026.82 b. Adustment Comp. 588,875.82 0.00 3. Materials on Hand 4. Earned Subject to Retention 20,570,621.76 240,026.82 5. Mobilization 2,069,500.00 0.00 6. Total Work Completed 22,640,121.76 7. Deductions -18,046.75 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 22,622,075.01 240,026.82 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 240,026.82