Dept. of Trans. PROGRESS Serial No. Contract No. 15-205-11-14 03-4F0704 PROGRESS PAYMENT VOUCHER %complete: %time: 33% 24% Location: Federal Project: 03-SAC-50-16.9/17.4 NH-P050(135) Progress payment No. 006 Payment period ending: 07-20-15 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD. DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,231,131.25 314,717.00 2. a. Extra Work 39,396.28 8,096.08 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 1,270,527.53 322,813.08 5. Mobilization 499,700.00 105,200.00 6. Total Work Completed 1,770,227.53 7. Deductions -2,000.00 8,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,768,227.53 436,013.08 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 436,013.08