Dept. of Trans. SEMI-FINAL Serial No. Contract No. 18-068-15-30 03-4F0904 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-SAC-5 NHPI-X067(75) Progress payment No. 006 Payment period ending: 08-09-17 MYERS & SONS CONSTRUCTION LP 4600 NORTHGATE BLVD #100 SACRAMENTO CA 95834 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,139,097.50 -34,452.50 2. a. Extra Work 146,270.84 125,154.02 b. Adustment Comp. 41,351.70 41,351.70 3. Materials on Hand 4. Earned Subject to Retention 2,326,720.04 132,053.22 5. Mobilization 204,000.00 0.00 6. Total Work Completed 2,530,720.04 7. Deductions -20,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,510,720.04 132,053.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 132,053.22