Dept. of Trans. SEMI-FINAL Serial No. Contract No. 15-320-15-57 03-4F3404 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-PLA-80-69.3/69.8 IMNH-804(201) Progress payment No. 007 Payment period ending: 09-11-15 GRANITE CONSTRUCTION COMPANY 585 WEST BEACH STREET WATSONVILLE CA 95076 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,190,914.75 44,700.50 2. a. Extra Work 267,250.62 0.00 b. Adustment Comp. -17,330.68 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,440,834.69 44,700.50 5. Mobilization 267,460.00 0.00 6. Total Work Completed 3,708,294.69 7. Deductions -23,544.92 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,684,749.77 44,700.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 44,700.50