Dept. of Trans. PROGRESS Serial No. Contract No. 22-201-14-13 03-4F3704 PROGRESS PAYMENT VOUCHER %complete: %time: 91% 80% Location: Federal Project: 03-NEV-174-3.0/3.9 HSST-P174(14) Progress payment No. 024 Payment period ending: 07-20-22 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,746,896.43 1,500.00 2. a. Extra Work 973,351.99 28,140.14 b. Adustment Comp. 54,704.32 0.00 3. Materials on Hand 4. Earned Subject to Retention 10,774,952.74 29,640.14 5. Mobilization 1,127,000.00 0.00 6. Total Work Completed 11,901,952.74 7. Deductions 0.00 4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,901,952.74 33,640.14 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 33,640.14