Dept. of Trans. PROGRESS Serial No. Contract No. 22-262-07-58 03-4F38U4 PROGRESS PAYMENT VOUCHER %complete: %time: 40% 41% Location: Federal Project: 03-YUB-70-16.2/25.8 HSNH-P070(144) Progress payment No. 008 Payment period ending: 09-20-22 DESILVA GATES CONSTRUCTION LP 11555 DUBLIN BLVD DUBLIN CA 94568 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 16,166,351.49 6,044,283.50 2. a. Extra Work 557,855.96 352,893.63 b. Adustment Comp. 150,000.00 150,000.00 3. Materials on Hand 336,309.00 296,911.65 4. Earned Subject to Retention 17,210,516.45 6,844,088.78 5. Mobilization 5,005,977.50 0.00 6. Total Work Completed 21,880,184.95 7. Deductions -1,848,771.29 -1,838,771.29 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 20,367,722.66 5,005,317.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 5,005,317.49