Dept. of Trans. PROGRESS Serial No. Contract No. 21-117-13-58 03-4F4204 PROGRESS PAYMENT VOUCHER %complete: %time: 15% 28% Location: Federal Project: 03-GLE-5-14.6/14.6 ACIM-057(100) Progress payment No. 005 Payment period ending: 04-20-21 TSI ENGINEERING INC 4600 ROSEVILLE RD #140 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 586,686.93 154,513.24 2. a. Extra Work 10,378.49 0.00 b. Adustment Comp. 3. Materials on Hand 29,372.00 0.00 4. Earned Subject to Retention 626,437.42 154,513.24 5. Mobilization 6. Total Work Completed 597,065.42 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 626,437.42 154,513.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 154,513.24