Dept. of Trans. PROGRESS Serial No. Contract No. 20-241-15-13 03-4F4304 PROGRESS PAYMENT VOUCHER %complete: %time: 52% 48% Location: Federal Project: 03-COL-5-24.3/24.3 CIMG-005-7(99) Progress payment No. 006 Payment period ending: 08-20-20 TSI ENGINEERING INC 4600 ROSEVILLE RD #140 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,063,342.24 310,103.21 2. a. Extra Work 79,507.49 22,243.35 b. Adustment Comp. -98,650.08 -98,650.08 3. Materials on Hand 4. Earned Subject to Retention 2,044,199.65 233,696.48 5. Mobilization 6. Total Work Completed 2,044,199.65 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,044,199.65 233,696.48 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 233,696.48