Dept. of Trans. PROGRESS Serial No. Contract No. 20-301-11-26 03-4F4304 PROGRESS PAYMENT VOUCHER %complete: %time: 69% 79% Location: Federal Project: 03-COL-5-24.3/24.3 CIMG-005-7(99) Progress payment No. 008 Payment period ending: 10-20-20 TSI ENGINEERING INC 4600 ROSEVILLE RD #140 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,471,648.67 257,818.96 2. a. Extra Work 355,181.24 18,973.75 b. Adustment Comp. -98,650.08 0.00 3. Materials on Hand 4. Earned Subject to Retention 2,728,179.83 276,792.71 5. Mobilization 6. Total Work Completed 2,728,179.83 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,728,179.83 276,792.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 276,792.71