Dept. of Trans. PROGRESS Serial No. Contract No. 21-083-11-33 03-4F4304 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 76% Location: Federal Project: 03-COL-5-24.3/24.3 CIMG-005-7(99) Progress payment No. 013 Payment period ending: 03-20-21 TSI ENGINEERING INC 4600 ROSEVILLE RD #140 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,495,318.24 46,127.00 2. a. Extra Work 514,689.12 15,946.88 b. Adustment Comp. -98,650.08 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,911,357.28 62,073.88 5. Mobilization 6. Total Work Completed 3,911,357.28 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 3,911,357.28 62,073.88 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 62,073.88