Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 21-323-09-31 03-4F4304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-COL-5-24.3/24.3 CIMG-005-7(99) Progress payment No. 018 Payment period ending: 09-21-21 TSI ENGINEERING INC 4600 ROSEVILLE RD #140 NORTH HIGHLANDS CA 95660 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,588,234.80 0.00 2. a. Extra Work 554,678.45 6,578.00 b. Adustment Comp. -98,650.08 0.00 3. Materials on Hand 4. Earned Subject to Retention 4,044,263.17 6,578.00 5. Mobilization 6. Total Work Completed 4,044,263.17 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,044,263.17 6,578.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 6,578.00