Dept. of Trans. PROGRESS Serial No. Contract No. 14-161-10-05 03-4F5504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 8% 0% 03-VAR Federal Project: NONE Progress payment No. 01 Payment period ending: 06-06-14 WABO LANDSCAPE & CONSTRUCTION, INC. 726 ALFRED NOBEL DRIVE HERCULES, CA 94547 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 191,701.25 191,701.25 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 191,701.25 191,701.25 5. Mobilization 6. Total Work Completed 191,701.25 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 191,701.25 191,701.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 191,701.25