Dept. of Trans. PROGRESS Serial No. Contract No. 19-357-09-10 03-4F6004 PROGRESS PAYMENT VOUCHER %complete: %time: 93% 93% Location: Federal Project: 03-NEV-80-1.2/9.4 SIMG-080-4(203) Progress payment No. 007 Payment period ending: 12-20-19 ROAD & HIGHWAY BUILDERS LLC PO BOX 70846 RENO NV 89570 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,154,963.22 53,865.00 2. a. Extra Work 257,358.21 171,630.98 b. Adustment Comp. -15,347.74 -15,347.74 3. Materials on Hand 4. Earned Subject to Retention 10,396,973.69 210,148.24 5. Mobilization 945,135.00 0.00 6. Total Work Completed 11,342,108.69 7. Deductions -2,000.00 -2,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,340,108.69 208,148.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 208,148.24