Dept. of Trans. PROGRESS Serial No. Contract No. 19-168-09-48 03-4F6304 PROGRESS PAYMENT VOUCHER %complete: %time: 42% 51% Location: Federal Project: 03-ED-49 SSTG-000C(485) 03-SIE-49 Progress payment No. 003 Payment period ending: 06-20-19 DREAMBUILDER CONSTRUCTION CORP 18543 YORBA LINDA BLVD #376 YORBA LINDA CA 92886 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 476,940.85 236,025.73 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 476,940.85 236,025.73 5. Mobilization 117,602.12 24,758.34 6. Total Work Completed 594,542.97 7. Deductions 0.00 5,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 594,542.97 265,784.07 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 265,784.07