Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 19-325-14-46 03-4F6304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 03-ED-49 SSTG-000C(485) 03-SIE-49 Progress payment No. 007 Payment period ending: 10-16-19 DREAMBUILDER CONSTRUCTION CORP 18543 YORBA LINDA BLVD #376 YORBA LINDA CA 92886 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,092,906.37 0.00 2. a. Extra Work 454,225.90 17,491.04 b. Adustment Comp. -30,544.80 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,516,587.47 17,491.04 5. Mobilization 123,791.70 0.00 6. Total Work Completed 1,640,379.17 7. Deductions -132,000.00 -84,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,508,379.17 -66,508.96 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate -66,508.96