Dept. of Trans. PROGRESS Serial No. Contract No. 24-325-06-48 03-4F6504 PROGRESS PAYMENT VOUCHER %complete: %time: 49% 45% Location: Federal Project: 03-YOL-50-0.0/2.5 ACNH-X113(36) 03-YOL-80-4.1/R11.4 Progress payment No. 020 Payment period ending: 11-20-24 FLATIRON-TEICHERT A JOINT VENTURE 1200 CONCORD AVE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 77,873,729.22 8,940,418.27 2. a. Extra Work 4,289,627.07 465,448.04 b. Adustment Comp. 4,467,519.19 3,120,588.46 3. Materials on Hand 6,596,662.28 102,010.32 4. Earned Subject to Retention 93,227,537.76 12,628,465.09 5. Mobilization 19,000,000.00 0.00 6. Total Work Completed 105,630,875.48 7. Deductions -28,090.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 112,199,447.76 12,627,465.09 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 12,627,465.09