Dept. of Trans. PROGRESS Serial No. Contract No. 25-055-10-05 03-4F6504 PROGRESS PAYMENT VOUCHER %complete: %time: 55% 46% Location: Federal Project: 03-YOL-50-0.0/2.5 ACNH-X113(36) 03-YOL-80-4.1/R11.4 Progress payment No. 023 Payment period ending: 02-20-25 FLATIRON-TEICHERT A JOINT VENTURE 1200 CONCORD AVE #465 CONCORD CA 94520 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 88,528,265.18 -145,062.94 2. a. Extra Work 8,371,266.71 3,640,911.08 b. Adustment Comp. 5,075,872.15 230,600.30 3. Materials on Hand 6,029,880.80 -705,217.55 4. Earned Subject to Retention 108,005,284.84 3,021,230.89 5. Mobilization 20,000,000.00 0.00 6. Total Work Completed 121,975,404.04 7. Deductions -19,090.00 -4,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 127,986,194.84 3,017,230.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 3,017,230.89