Dept. of Trans. PROGRESS Serial No. Contract No. 15-233-14-27 03-4F6704 PROGRESS PAYMENT VOUCHER %complete: %time: 77% 85% Location: Federal Project: 03-NEV-49-3.4 NONE Progress payment No. 002 Payment period ending: 08-20-15 AMERICA PACIFIC CONSTRUCTION 201 LAUREL AVE # 13 BREA CA 92821 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 170,442.50 167,202.50 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 170,442.50 167,202.50 5. Mobilization 6. Total Work Completed 170,442.50 7. Deductions -10,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 160,442.50 157,202.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 157,202.50